Updated
Updated · WBAL TV Baltimore · Apr 28
Maryland and Federal Officials Drop Kiewit for Key Bridge Rebuild Phase 2
Updated
Updated · WBAL TV Baltimore · Apr 28

Maryland and Federal Officials Drop Kiewit for Key Bridge Rebuild Phase 2

13 articles · Updated · WBAL TV Baltimore · Apr 28
  • Kiewit, previously awarded a $73 million contract for Phase 1, will not continue to Phase 2 after failing to agree on price and timeline with Maryland officials.
  • Governor Wes Moore cited independent cost estimates showing Kiewit's proposal as unreasonably high. Work at the bridge site will continue, with Kiewit completing Phase 1 tasks such as foundation piling and temporary trestle construction.
  • The decision follows months of negotiations and rising cost estimates, with the rebuild now projected at up to $5.2 billion. A new contractor will be selected for Phase 2, covering final design and engineering.
How much did Kiewit's rejected bid exceed Maryland's $5.2 billion estimate for the Key Bridge rebuild?
Is Kiewit's bidding strategy becoming a liability after losing two major projects over high cost estimates?
Will finding a new contractor push the Key Bridge's delayed 2030 opening date even further into the future?
How will Maryland manage Kiewit's ongoing $500M Phase 1 work after firing them from Phase 2?
With costs already tripling, how will Maryland prevent the final bill from soaring even higher with a new builder?
What specific oversight will federal officials use to ensure taxpayer funds are not wasted in the new contract?