Three Subcontractors File $900,000 in Liens on Obama Center Home Court as Cost Tops $1 Billion
Updated
Updated · Fox News · Jul 25

Three Subcontractors File $900,000 in Liens on Obama Center Home Court as Cost Tops $1 Billion

1 articles · Updated · Fox News · Jul 25

Summary

  • $900,000 in new mechanics liens were filed by three subcontractors over unpaid work on the Obama Presidential Center's Home Court, covering structural steel, excavation and concrete, and gym flooring.
  • Area Erectors seeks nearly $620,000, CSI 3000 about $236,000, and Floors Incorporated nearly $25,000; the claims were recorded around the center's June 19 opening and only recently appeared online after a county posting delay.
  • Home Court was built under a separate contract by Elevate Design Builders rather than the main campus manager, Lakeside Alliance, and the liens do not by themselves establish which entity is legally responsible for payment.
  • Another three previously unreported liens totaling about $557,000 were also identified elsewhere on the project, adding to earlier disputes that included a more than $40 million claim later replaced by a surety bond.
  • The new claims deepen construction troubles at the Chicago project, whose estimated cost has climbed from about $350 million to more than $1 billion amid legal and contracting disputes.